9.9 Oxygen Lance
Ⅰ Dominant Items
9.9.1 The hydrostatic test of oxygen lance must meet the requirement of the design technical document.
Quantity to be checked:100%.
Inspection method:Observe,and check the pressure test record.
9.9.2 The parts,components and pipeline of the equipment contact with oxygen must not be stained with oil or grease.
Quantity to be checked:100%.
Inspection method:Check the record of degreasing,and check via wiping with white filter paper or exposing it under the ultraviolet lamp.
Ⅱ General Items
9.9.3 The allowable deviation for installation of oxygen lance shall comply with the requirements in Table 9.9.3.
Quantity to be checked:100%.
Inspection method:See Table 9.9.3.
Table 9.9.3 Allowable deviation for installation of oxygen lance